DESIGN · IKB-047
DfMA: How Cutting Part Count Slashes Assembly Cost
Consolidating a 12-piece bracket assembly into 4 parts can cut assembly time by two-thirds. Here's how to decide using Boothroyd-Dewhurst's part-combination criteria, with a worked example.
During a design review I was handed a bracket assembly made up of 12 parts: a base plate, two side supports, four screws, four washers, and a spacer. The drawing was correct, tolerances were reasonable, and the FEA results showed an adequate factor of safety. But on the assembly line, the operator building this bracket repeated the same steps every cycle: flip the part, find the correct orientation, grab the screw, fit the washer, torque it down. Twelve parts meant twelve separate decision points.
This is exactly where DfMA (Design for Manufacture and Assembly) comes in: fewer parts generally mean shorter assembly time, lower error probability, fewer inventory line items, and less quality-control burden. In this post I walk through the logic of the Boothroyd-Dewhurst approach, the three questions that drive part-combination decisions, and the real numbers behind reducing a 12-part bracket assembly to 4 parts.
The Boothroyd-Dewhurst approach and the DFA index#
The DFA (Design for Assembly) method developed by Geoffrey Boothroyd and Peter Dewhurst in the 1980s assigns a standard time to every assembly operation: handling, orientation, and insertion. These times are read from tables based on a part’s symmetry, weight, flexibility, and ease of insertion. Total assembly time together with part count produces a DFA index that reflects design efficiency:
$$ E_{ma} = \frac{N_{min} \cdot t_{min}}{T_{ma}} $$
Here \(N_{min}\) is the theoretical minimum number of parts required, \(t_{min}\) is the ideal time per part (typically assumed to be ~3 seconds), and \(T_{ma}\) is the actual total assembly time. A low index indicates “unnecessary” part proliferation in the design. It’s healthier to treat this number as a common ground for discussion among designers rather than a strict target; actual figures should always be validated with the production line’s own time study.
Three combination criteria#
To determine whether a part needs to remain separate, Boothroyd-Dewhurst propose three questions. If the answer to all three is “no” for a given part, it’s a candidate for combination with its neighbor:
- Does the part move independently relative to other already-assembled parts? (a hinge, sliding surface, or rotating shaft, for example)
- Must the part be made of a different material? (electrical insulation, thermal isolation, a different hardness requirement, etc.)
- Must the part remain separate so that other parts can be assembled or disassembled? (for example, access to a part underneath a cover)
In the bracket example, the side supports moved together with the base plate, were not a different material, and did not need to be separate for assembly or disassembly — “no” to all three. The spacer was in the same situation. The screws, however, must remain separate as fasteners; combining them would require a separate decision (for example, switching to a welded or riveted fixed joint).
Example: 12-part bracket assembly reduced to 4 parts#
In the redesign we applied the three questions: the base plate, two side supports, and the spacer merged into a single machined or cast housing; flange and mounting surfaces were machined onto the same part. All that remained were the two screws required for the fastening function and a cover/pin that determines assembly sequence. Result: 4 parts instead of 12.
When proposing consolidation, the manufacturing method needs to be considered together with it. Producing a single part by casting or machining increases tooling cost; always check whether this cost exceeds the assembly savings at low production volumes. Saying “let’s combine them” without calculating the break-even volume can sometimes raise total cost.
Assembly time comparison#
The following calculation uses representative values close to standard DFA handbook time tables; it should be validated with a stopwatch study on the actual production line.
Worked example
Old assembly (12 parts): base plate handling+insertion 4.0 s; 2 side brackets (orientation required) each 9.0 s → 18.0 s; 4 screws each handling 3.0 s + insertion 6.0 s = 9.0 s → 36.0 s; 4 washers each 6.0 s → 24.0 s; 1 spacer 7.0 s.
$$ T_{old} = 4.0+18.0+36.0+24.0+7.0 = 89.0\,\mathrm{s} $$
New assembly (4 parts): consolidated housing (self-aligning) 5.0 s; 2 screws each 9.0 s → 18.0 s; 1 cover/pin 6.0 s.
$$ T_{new} = 5.0+18.0+6.0 = 29.0\,\mathrm{s} $$
Time reduction: $$ \frac{89.0-29.0}{89.0} \approx 0.67 \Rightarrow 67\% $$ ✓ significant gain
DFA index: assuming a theoretical minimum part count of \(N_{min}=3\) (housing, fastener, cover), the old design gives \(E_{ma}\approx 3/12=25\%\), and the new design \(E_{ma}\approx 3/4=75\%\).
Using a representative labor rate of $0.35/minute, the unit cost of the old assembly is roughly $0.52, versus $0.17 for the new assembly — a savings of about $0.35 per unit. At an annual production volume of 200,000 units, that’s roughly $70,000 in assembly labor savings alone. Against this, the casting or machining cost of the consolidated housing must be calculated separately; don’t decide without comparing total unit cost (part + assembly) across both scenarios.
Practical tips in CAD software#
- SolidWorks: Use Weldments or multibody part modeling to keep the before/after scenario in the same file; track actual part count with the Cut List feature. The Costing tool lets you roughly estimate casting/machining cost at the design stage.
- Siemens NX: Keep the consolidated housing’s relationship to neighboring parts live using WAVE geometry links within Assembly Design; with Teamcenter integration, compare how the BOM (bill of materials) and cost change as part count drops.
- CATIA V5: Use the DMU Fitting/Process Simulation module to virtually compare the duration of old and new assembly sequences, and use Knowledgeware rules to automatically verify that the tolerance stack-up is still valid after consolidation.
When not to combine#
Part combination isn’t always the right answer. In a housing reduced to a single part, localized damage (a crack, a worn hole) requires replacing the entire assembly; service and spare-parts cost can increase. Also, at interfaces requiring different materials (for example, a surface requiring electrical insulation), combination is physically impossible. Any part that answers “yes” to one of the three questions should remain separate; otherwise you lose functionality.
Key takeaways#
- Parts that answer “no” to all three Boothroyd-Dewhurst questions (independent motion, different material, assembly/disassembly necessity) are candidates for combination.
- When the 12-part bracket assembly was reduced to 4 parts, assembly time dropped by 67% in this example, and the DFA index rose from 25% to 75%.
- Assembly savings from reducing part count must be weighed against increased tooling cost through total unit cost comparison.
- Reducing to a single part must not violate constraints like serviceability and differing material requirements.
Take an assembly drawing you’re working on and ask the three questions for each part: is there independent motion, is a different material required, does it need to stay separate for assembly/disassembly? If the answer is “no” to all three, seriously evaluate combining that part with its neighbor — but don’t decide without factoring in tooling cost and the service scenario.